When calculating weights for contract purposes, deductions are made for material removed by none of the following options

Prepare for the California Structural Steel Contractor (C-51 License) Exam. Study with flashcards and multiple-choice questions with hints and explanations. Get ready to succeed!

Multiple Choice

When calculating weights for contract purposes, deductions are made for material removed by none of the following options

Explanation:
When calculating weights for contract purposes, the basis is the weight of steel as it will be used in the project, and deductions for pieces removed or scrap are not applied to reduce that contract weight. Field removals, shop fabrication removals, or salvage material are not subtracted from the contract weight in this context; any salvage or adjustments would be handled separately outside the basic weight calculation. In short, none of those categories are deductions for the contract weight, so the correct answer is that none of the listed options represent a deduction.

When calculating weights for contract purposes, the basis is the weight of steel as it will be used in the project, and deductions for pieces removed or scrap are not applied to reduce that contract weight. Field removals, shop fabrication removals, or salvage material are not subtracted from the contract weight in this context; any salvage or adjustments would be handled separately outside the basic weight calculation. In short, none of those categories are deductions for the contract weight, so the correct answer is that none of the listed options represent a deduction.